Wind Farm Development Process

Site Selection Overview

Estimated reading: 4 minutes 50 views Contributors

Selecting the right location for a wind farm is one of the most critical steps in the development process. A well-chosen site maximizes energy production, minimizes environmental and community impact, and ensures financial viability. This phase involves assessing wind resources, land suitability, grid access, and regulatory considerations to determine whether a site is viable for wind energy development.


๐Ÿ“‚ Key Factors in Site Selection

1. Wind Resource Assessment

The energy output of a wind farm depends on the speed, direction, and consistency of wind at a site. Developers assess wind resources using:

  • Historical Weather Data โ€“ Long-term meteorological records from sources like the Met Office.
  • GIS Wind Mapping Tools โ€“ National wind atlases and spatial datasets.
  • On-Site Measurements โ€“ Deploying LiDAR (Light Detection and Ranging) or meteorological masts for real-world wind speed data.

Sites with higher and more consistent wind speeds are preferred, as energy output increases exponentially with wind speed.


2. Land Ownership & Lease Agreements

Wind farms require long-term access to land, typically through lease agreements between developers and landowners. Key considerations include:

  • Land Availability โ€“ Ensuring sufficient space for turbine layout, infrastructure, and access roads.
  • Land Use Compatibility โ€“ Assessing how turbines integrate with farming, forestry, or other existing land uses.
  • Ownership & Legal Constraints โ€“ Understanding property boundaries, rights of way, and any existing land agreements.

In most cases, landowners receive annual payments for hosting turbines, which provide a stable additional income.


3. Grid Connection Feasibility

For a wind farm to deliver power to consumers, it must connect to the electricity grid. The feasibility of grid access depends on:

  • Proximity to Existing Grid Infrastructure โ€“ Distance to substations, overhead power lines, and connection points.
  • Network Capacity โ€“ Whether the local grid can accommodate additional electricity generation.
  • Grid Application & Costs โ€“ The process of applying for a connection with Distribution Network Operators (DNOs) and estimating costs for infrastructure upgrades.

Grid constraints can significantly impact project feasibility and costs, making early engagement with DNOs essential.


4. Planning & Environmental Considerations

Before advancing a site, developers review local planning policies and environmental constraints to ensure that the project is likely to receive approval. Factors include:

  • Local & National Planning Policy โ€“ Identifying areas designated for wind development.
  • Land Designations & Protected Areas โ€“ Avoiding National Parks, AONBs (Areas of Outstanding Natural Beauty), SSSIs (Sites of Special Scientific Interest), and heritage sites.
  • Aviation & Radar Restrictions โ€“ Ensuring compliance with air traffic control and military radar requirements.

(For more details, see Planning & Consenting and Environmental & Social Considerations.)


5. Financial & Technical Viability

A viable wind farm must be economically sustainable. Early feasibility studies include:

  • Energy Yield Projections โ€“ Estimating how much electricity the site can generate annually.
  • Development Costs โ€“ Assessing expenses related to land leases, permitting, grid connection, and construction.
  • Revenue Models โ€“ Evaluating potential income from government incentives, Contracts for Difference (CfD), and Power Purchase Agreements (PPAs).

Developers use financial modelling to determine whether a site is commercially viable before proceeding with further studies.


๐Ÿ“Œ Timeline for Site Selection & Feasibility

PhaseKey ActivitiesTypical Duration
Initial Site ScreeningGIS mapping, wind resource analysis, landowner outreach3โ€“6 months
Wind MonitoringLiDAR or meteorological mast deployment12โ€“24 months
Grid Feasibility StudyDNO engagement, capacity checks, cost estimates3โ€“9 months
Planning Pre-ScreeningReviewing land constraints, planning policies, and permitting risks3โ€“6 months
Financial Pre-FeasibilityPreliminary cost analysis, revenue modelling, risk assessment3โ€“6 months

A site that passes all feasibility assessments moves to the Development & Permitting phase, where detailed technical and environmental studies begin.


๐Ÿ”— Related Topics

  • Planning & Consenting โ†’ Navigating the UK planning and permitting process.
  • Environmental & Social Considerations โ†’ Addressing ecological, landscape, and social impacts.
  • Grid Connection & Infrastructure โ†’ Understanding grid application processes and technical requirements.
  • Investment & Commercial Strategy โ†’ Financial modelling, revenue sources, and cost considerations.

Summary

Site selection is a foundational stage in wind farm development, determining whether a project is technically, environmentally, and commercially viable. Careful assessment of wind resources, land access, grid connection, planning policies, and financial feasibility ensures that only the most promising sites move forward in the development pipeline.


Summary of Wind farm power density optimization according to the area size using a novel genetic algorithm

The paper “Wind farm power density optimization according to the area size

Site Design Research

Microgrids: A Primer

Introduction A microgrid is a localized group of electricity sources and loads t

Grid Issues

Summary: Assessment of Simulation and Modelling Errors for Three CFD Wind Models

The paper “Assessment of Simulation and Modelling Errors for Three CFD Win

Wind Energy Policy & Advocacy

Working with Landowners and Farmers

Wind energy development depends on strong partnerships with landowners and farme

Community Engagement

Engaging with local communities is a key part of wind farm development. Early, t

Stakeholders in Wind Energy

Wind energy projects involve a wide range of stakeholders, each with different i

UK Distribution Network Operators (DNOs) A Complete Guide

What is a Distribution Network Operator (DNO)? A Distribution Network Operator (

Grid Connection and Infrastructure

For a wind farm to deliver electricity to consumers, it must be connected to the

Engineering & Technical Studies

The success of a wind farm depends on careful engineering and technical assessme