Wind Farm Development Process

Planning and Consenting

Estimated reading: 5 minutes 57 views Contributors

The planning and consenting process for wind farms varies across the UK nations, as each has its own regulatory framework, planning policies, and approval processes. While the overall principles remain similar—covering environmental assessments, grid connections, and community engagement—the planning authority, approval thresholds, and specific requirements differ between England, Scotland, Wales, and Northern Ireland.

This section outlines the key regulations and consenting processes for wind energy development in each UK nation.


📂 Key Aspects of Planning & Consenting

1. UK Planning Laws & Regulations

The planning process depends on the size and location of the project:

England

  • Projects under 50 MW → Determined by Local Planning Authorities (LPA) under the Town and Country Planning Act 1990 and National Planning Policy Framework (NPPF).
  • Projects over 50 MW → Considered Nationally Significant Infrastructure Projects (NSIPs) and require a Development Consent Order (DCO) from the Secretary of State for Energy Security and Net Zero, assessed by the Planning Inspectorate.
  • Onshore Wind Policy Changes: Since 2015, restrictive planning rules have made it difficult to develop new onshore wind projects. However, recent changes suggest a shift towards easing restrictions to support new developments.
  • Offshore Wind (over 100 MW) → Requires a DCO and approval from the Marine Management Organisation (MMO) under the Marine and Coastal Access Act 2009.

Scotland

  • Projects up to 50 MW → Determined by local authorities under the Town and Country Planning (Scotland) Act 1997.
  • Projects over 50 MW → Considered Section 36 Developments under the Electricity Act 1989, requiring approval from the Scottish Ministers via the Energy Consents Unit (ECU).
  • Strategic Focus: Scotland has a more supportive policy environment for onshore wind, with clear National Planning Framework (NPF4) policies encouraging new developments.
  • Offshore Wind: Applications are handled through Marine Scotland, which oversees marine licensing and planning.

Wales

  • Projects under 10 MW → Assessed by Local Planning Authorities under the Town and Country Planning Act 1990.
  • Projects between 10 MW and 350 MW → Determined by the Welsh Ministers under the Developments of National Significance (DNS) process.
  • Projects over 350 MW → Considered NSIPs, requiring a DCO from the Secretary of State for Energy Security and Net Zero.
  • Planning Policy: The Future Wales: National Plan 2040 supports onshore wind expansion, identifying Pre-Assessed Areas for Wind Energy to streamline planning approvals.

Northern Ireland

  • Projects under 50 MW → Assessed by local councils under the Planning Act (Northern Ireland) 2011.
  • Projects over 50 MW → Defined as Regionally Significant Developments (RSDs), requiring approval from the Department for Infrastructure (DfI).
  • Challenges: Northern Ireland has one of the most restrictive planning environments for wind energy, with a high level of public inquiries and planning objections.

2. Environmental Impact Assessment (EIA)

Wind farms typically require an Environmental Impact Assessment (EIA) to evaluate potential impacts on the environment, wildlife, and communities.

Key Steps in the EIA Process:

  1. Screening – Determines whether an EIA is required based on project size and environmental sensitivity.
  2. Scoping – Defines which environmental aspects must be assessed, including:
    • Wildlife & Habitat Impact (birds, bats, and protected species).
    • Landscape & Visual Effects (impact on scenic views and heritage sites).
    • Noise & Shadow Flicker (effects on nearby properties).
  3. Impact Assessment & Mitigation – Studies are conducted to identify risks and propose mitigation strategies.
  4. Stakeholder Consultation – Findings are shared with planning authorities, statutory consultees, and local communities.
  5. Decision & Conditions – If approved, conditions may require ongoing monitoring and mitigation measures.

The specific requirements for EIAs differ across the UK:

  • England & Wales → Governed by the Town and Country Planning (Environmental Impact Assessment) Regulations 2017.
  • Scotland → Regulated by the Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2017.
  • Northern Ireland → Falls under the Planning (Environmental Impact Assessment) Regulations (Northern Ireland) 2017.

An EIA typically takes 12–24 months, depending on project complexity.

(For more details, see Environmental & Social Considerations.)


3. Community Engagement & Consultation

Public engagement is a critical factor in securing planning approval for wind farms. Developers are expected to consult with communities early to address concerns and build support.

Legal Consultation Requirements:

  • England → Onshore wind projects require community backing under local planning rules. Offshore projects undergo public engagement through the Planning Inspectorate.
  • Scotland → Developers must follow Good Practice Principles for Community Benefits from Onshore Renewable Energy Developments, including direct engagement and benefit-sharing schemes.
  • Wales → The Developments of National Significance (DNS) process mandates early public exhibitions and consultations.
  • Northern Ireland → Community consultation is required for large-scale projects, with detailed public engagement reports submitted with planning applications.

Common Public Concerns & How They Are Addressed:

  • Visual Impact → Turbine layout adjustments to minimize visibility from key viewpoints.
  • Noise & Shadow Flicker → Positioning turbines to comply with strict noise regulations and flicker reduction measures.
  • Wildlife Protection → Modifying turbine locations or implementing mitigation measures for bird and bat populations.
  • Community Benefit Schemes → Many developers provide funding for local projects, such as infrastructure improvements, education initiatives, or environmental programs.

(For more details, see Stakeholder Engagement & Community Relations.)


📌 Planning & Consenting Timeline

StageKey ActivitiesTypical Duration
Site Assessment & Pre-ApplicationFeasibility studies, early engagement, EIA screening12–24 months
Planning Application SubmissionSubmitting EIA reports, community consultation results6–12 months
Regulatory Review & DecisionLocal/national authority review, potential public inquiry12–36 months
Post-Approval ComplianceMeeting conditions before construction starts3–12 months

Total planning time can range from 2 to 5 years, depending on project size and location.


🔗 Related Topics

  • Environmental & Social Considerations → Addressing ecological and social impacts.
  • Site Selection & Screening → Finding and evaluating potential wind farm locations.
  • Grid Connection & Infrastructure → Securing grid capacity and connection approvals.

Summary

The planning and consenting process for wind farms is nation-specific, with different approval thresholds, environmental requirements, and public engagement expectations across England, Scotland, Wales, and Northern Ireland. Developers must navigate planning laws, EIAs, and community consultation to secure approval and move towards construction.


Summary of Wind farm power density optimization according to the area size using a novel genetic algorithm

The paper “Wind farm power density optimization according to the area size

Site Design Research

Microgrids: A Primer

Introduction A microgrid is a localized group of electricity sources and loads t

Grid Issues

Summary: Assessment of Simulation and Modelling Errors for Three CFD Wind Models

The paper “Assessment of Simulation and Modelling Errors for Three CFD Win

Wind Energy Policy & Advocacy

Working with Landowners and Farmers

Wind energy development depends on strong partnerships with landowners and farme

Community Engagement

Engaging with local communities is a key part of wind farm development. Early, t

Stakeholders in Wind Energy

Wind energy projects involve a wide range of stakeholders, each with different i

UK Distribution Network Operators (DNOs) A Complete Guide

What is a Distribution Network Operator (DNO)? A Distribution Network Operator (

Grid Connection and Infrastructure

For a wind farm to deliver electricity to consumers, it must be connected to the

Engineering & Technical Studies

The success of a wind farm depends on careful engineering and technical assessme